NEOM ends Trojena Ski Village contract with Eversendai effective March 2026

Eversendai added that it believes the termination “has happened due to the current geopolitical situation in the Middle East”

Staff Writer
Trojena, NEOM
Image: NEOM

Article summary

AI Generated

Eversendai Corporation Berhad has received a notice of termination for its Trojena Ski Village structural steel contract from NEOM, effective March 26, 2026. The company believes the termination is due to the current geopolitical situation in the Middle East and is preparing claims for compensation. Eversendai's order book remains strong at RM2.02 billion, excluding the terminated contract.

Key points

  • Eversendai's Trojena Ski Village contract terminated by NEOM, effective March 26, 2026.
  • Company claims full commitment and delivery, citing geopolitical issues for termination.
  • Eversendai preparing claims for compensation and remains optimistic about future projects.

Eversendai Corporation Berhad has confirmed that it has received a notice of termination for its Trojena Ski Village structural steel contract from NEOM, with the termination set to take effect on March 26, 2026.

The company referred to its earlier announcement dated March 13, 2024, in which it disclosed that it had secured the contract in collaboration with Al Bawani Co in the Kingdom of Saudi Arabia.

Eversendai stated that it had “fully committed and delivered the project as per the contractual obligations with no compromise to safety and quality” up to the date of the notice. The company added that it believes the termination “has happened due to the current geopolitical situation in the Middle East.”

Trojena Ski Village steel works contract terminated by NEOM

The group said it is preparing documentation to substantiate the progress of the project carried out in accordance with the contract up to the termination date. This includes commercial claims related to the termination and associated demobilisation costs, which it stated “should be compensated by the client.”

Eversendai added, “We strongly believe that our fully substantiated claims shall be fairly compensated by the client.”

Advertisement

The company reported that its current order book stands at RM2.02 billion, excluding the remaining works for the Trojena Ski Village contract. Its tender book stands at RM18.4 billion.

Eversendai stated that it is close to concluding new projects which are expected to add to its existing order book.

The group said its operations in the Middle East remain stable despite the current geopolitical situation. It added that it remains “highly optimistic in securing more projects across the Group to further improve our financial performance going forward.”